CISA Domain 1B-1 Practice Test 002

This practice test covers Domain 1 (Information Systems Auditing Process) Subdomain B-1 (Audit Project Management) from the CISA exam content outline.

These questions are inspired by the ISACA CISA exam and are designed to help you test your knowledge of information systems auditing, governance, risk management, IT operations, business resilience, and information asset protection.

These are not official exam questions or brain dumps. They are original scenario-based questions created to reflect the audit judgment, control evaluation, and risk-based decision-making skills tested in the CISA exam.

Note: CISA and Certified Information Systems Auditor are registered trademarks of ISACA. This content is not affiliated with or endorsed by ISACA.

To choose CISA practice tests based on specific domains and subdomains, click that link.

CISA 1B-1 Audit Project Management Practice Test 002
10 questions • Single best answer
Question 1
A state university's internal audit function is launching its first review of a newly outsourced student records platform. The engagement lead has been given a fixed budget and a reporting deadline set by the audit committee, but no detailed plan yet exists. What should the audit project manager do FIRST when building the engagement plan?
    Question 2
    Midway through fieldwork on a manufacturer's ERP access review, business managers ask the audit team to also examine unrelated payroll processing complaints. Satisfying the request would consume roughly a third of the remaining engagement hours. What is the audit project manager's BEST course of action?
      Question 3
      An IS audit engagement is seventy percent through its allotted hours, but only about forty percent of the planned test procedures are complete. Two team members have been reassigned to another review, and the engagement manager has not reported any variance to the chief audit executive. Which of the following is the MOST significant concern?
        Question 4
        A bank's audit plan includes a review of a newly deployed cloud container platform, but no team member has relevant technical experience. The chief audit executive intends to engage an external specialist to perform the technical procedures. Which of the following is MOST important for the audit project manager to establish before the work begins?
          Question 5
          During a quality review of a completed healthcare application audit, the reviewer finds detailed workpapers whose conclusions appear supported by the evidence on file. The engagement was staffed entirely by first-year auditors, and no workpaper shows evidence of supervisory sign-off. Which finding should the reviewer report as MOST significant?
            Question 6
            A government agency's IS audit team identifies a significant weakness in payment processing during the second week of a twelve-week engagement, and the weakness could permit duplicate disbursements. The approved engagement plan provides for findings to be communicated in the final report. What should the audit project manager do?
              Question 7
              An insurance company's annual audit plan allocates fixed hours to each engagement. Two high-risk reviews are now scheduled to run concurrently with a regulatory examination that will require the same audit staff for several weeks. Which action by the chief audit executive is MOST appropriate?
                Question 8
                An IS auditor notes that an engagement work program was modified three times during fieldwork to drop procedures the team could not complete on schedule. The modifications were directed verbally by the engagement lead and are not reflected anywhere in the workpapers. What is the GREATEST risk?
                  Question 9
                  A retail organization's internal audit function is adopting an agile approach that delivers observations to management in short iterative cycles rather than in a single year-end report. The audit committee is concerned that quality may vary between cycles. Which control BEST preserves audit quality under this approach?
                    Question 10
                    During planning for an external audit of a manufacturer's third-party logistics system, the team learns that right-to-audit access must be requested from the vendor thirty days in advance. The engagement is scheduled to begin in two weeks and the vendor has not been contacted. What should the audit project manager do FIRST?