CISA Domain 3A-1 Practice Test 001

This practice test covers Domain 3 (Information Systems Acquisition, Development & Implementation) Subdomain A-1 (Project Governance and Management) from the CISA exam content outline.

These questions are inspired by the ISACA CISA exam and are designed to help you test your knowledge of information systems auditing, governance, risk management, IT operations, business resilience, and information asset protection.

These are not official exam questions or brain dumps. They are original scenario-based questions created to reflect the audit judgment, control evaluation, and risk-based decision-making skills tested in the CISA exam.

Note: CISA and Certified Information Systems Auditor are registered trademarks of ISACA. This content is not affiliated with or endorsed by ISACA.

To choose CISA practice tests based on specific domains and subdomains, click that link.

CISA 3A-1 Project Governance and Management Practice Test 001
10 questions • Single best answer
Question 1
A retail organization is launching a multiyear ERP program. The IS auditor observes that the project steering committee lacks an executive sponsor, meets only sporadically, and the IT project manager unilaterally approves all scope and budget changes without escalation. Which of the following is the MOST significant project governance concern?
    Question 2
    An IS auditor begins a review of project governance for a newly approved software initiative at an energy company. Before assessing whether controls are adequate, the auditor wants to understand how decisions are authorized, escalated, and monitored. Which of the following should the auditor review FIRST?
      Question 3
      During a review of IT project governance at an insurance company, the IS auditor wants assurance that an in-flight project remains aligned with strategic business objectives as it progresses through successive phases. Market conditions have shifted since approval, yet management insists the initiative remains on track. Which of the following provides the BEST evidence of ongoing alignment?
        Question 4
        An audit manager evaluates governance of a large system implementation at a manufacturing firm. The project steering committee approves initial funding but then delegates all stage-gate go/no-go decisions entirely to the project manager, who also defines the criteria for passing each gate. Which of the following is the MOST appropriate recommendation?
          Question 5
          A post-approval review of a bank's digital lending project finds the original business case was never revised despite a 40% budget increase and a scope expansion into two new markets. Governance meetings continued each month without reassessing viability or expected benefits. Which finding is MOST significant to the IS auditor?
            Question 6
            While planning an audit of project governance at a logistics company, an IS auditor finds that accountability for project outcomes is unclear, several managers each claim decision authority, and no single individual is answerable for benefits realization. Which of the following should the auditor do FIRST before forming any conclusion?
              Question 7
              An IS auditor reviews how a healthcare organization selects and prioritizes its IT projects. Numerous initiatives are funded simultaneously with no ranking against strategic criteria, resources are frequently reallocated mid-stream, and several projects appear to duplicate one another's objectives. Which of the following controls would BEST address this condition?
                Question 8
                An IS auditor questions the reliability of project status reports at a telecommunications company because the project manager self-reports progress with no independent validation, and reported completion has remained at ninety percent for several consecutive reporting cycles. Which of the following provides the BEST assurance that reported project status is accurate?
                  Question 9
                  During an audit of IT project governance at a utility, the IS auditor is asked to clarify decision accountability between the oversight body and day-to-day project management. Which of the following is the responsibility of the project steering committee rather than the project manager during the execution of the project?
                    Question 10
                    An IS auditor is invited to join the steering committee of a new financial system project as a voting member because of recognized expertise in application controls and risk. The committee makes binding funding and scope decisions. Which of the following is the auditor's BEST course of action to preserve audit independence?