CISA Domain 3B-3 Practice Test 002

This practice test covers Domain 3 (Information Systems Acquisition, Development & Implementation) Subdomain B-3 (System Migration, Infrastructure Deployment, and Data Conversion) from the CISA exam content outline.

These questions are inspired by the ISACA CISA exam and are designed to help you test your knowledge of information systems auditing, governance, risk management, IT operations, business resilience, and information asset protection.

These are not official exam questions or brain dumps. They are original scenario-based questions created to reflect the audit judgment, control evaluation, and risk-based decision-making skills tested in the CISA exam.

Note: CISA and Certified Information Systems Auditor are registered trademarks of ISACA. This content is not affiliated with or endorsed by ISACA.

To choose CISA practice tests based on specific domains and subdomains, click that link.

CISA 3B-3 System Migration, Infrastructure Deployment, and Data Conversion Practice Test 002
10 questions • Single best answer
Question 1
An external audit firm engaged by a credit union is reviewing the planned conversion of member loan records to a new lending platform. Conversion scripts have passed unit testing, but the project plan does not describe how record counts and loan balances will be reconciled between the legacy and target systems. Which recommendation is MOST appropriate before the conversion proceeds?
    Question 2
    During the conversion of claims history for a health insurer's new adjudication system, the error log shows that 2 percent of source records were rejected and written to a suspense file. The project manager plans to proceed with go-live next week and correct the rejected records afterward. What should the IS auditor do FIRST?
      Question 3
      A government ministry deploys new virtual server infrastructure for its benefits portal using infrastructure-as-code templates that passed a security review. The IS auditor finds that engineers manually modified several production servers after deployment to resolve performance issues, and the templates were not updated. Which recommendation is MOST appropriate?
        Question 4
        A regional bank plans a single-weekend cutover of its core deposit system during a holiday. While reviewing the cutover plan, the IS auditor notes that the plan contains detailed conversion steps but no defined rollback criteria, go/no-go decision point, or procedures for reactivating the legacy system. Which risk is MOST significant?
          Question 5
          A pharmaceutical distributor has migrated inventory and lot-tracking data from an on-premises warehouse system to a cloud platform. Regulators require complete traceability of product lots, and the IS auditor must conclude whether the migrated data is complete and accurate. Which of the following is the BEST evidence?
            Question 6
            A national retail chain is migrating customer loyalty data to a new marketing platform. The IT project team defined all field mapping and transformation rules and plans to approve the converted results itself before go-live, noting that business users are busy with seasonal sales. Which recommendation is MOST appropriate?
              Question 7
              An insurance company ran its legacy and new policy administration systems in parallel for one billing cycle. Premium calculations differed for several hundred policies, and to meet the go-live date the project team manually adjusted the new system's outputs to match the legacy results. What is the IS auditor's GREATEST concern?
                Question 8
                A state university hires a consulting firm to perform conversion rehearsals for its new financial aid system. The IS auditor finds that full copies of production data, including student identifiers and family income details, were loaded into the rehearsal environment, where all consultants have unrestricted access. Which recommendation is MOST appropriate?
                  Question 9
                  An audit manager at a securities firm is planning a review of an upcoming data center relocation that will move trading, settlement, and reporting systems to a new facility. Audit resources are limited to three weeks of fieldwork. Which area should receive the HIGHEST priority in the audit plan?
                    Question 10
                    A post-implementation review of a manufacturer's ERP migration finds that historical purchasing transactions were converted without their original created-by and approval timestamp fields because the mapping specification omitted them. Regulations require the company to retain this audit trail for seven years. Which recommendation is MOST appropriate?