CISA Domain 3B-4 Practice Test 001

This practice test covers Domain 3 (Information Systems Acquisition, Development & Implementation) Subdomain B-4 (Post-implementation Review) from the CISA exam content outline.

These questions are inspired by the ISACA CISA exam and are designed to help you test your knowledge of information systems auditing, governance, risk management, IT operations, business resilience, and information asset protection.

These are not official exam questions or brain dumps. They are original scenario-based questions created to reflect the audit judgment, control evaluation, and risk-based decision-making skills tested in the CISA exam.

Note: CISA and Certified Information Systems Auditor are registered trademarks of ISACA. This content is not affiliated with or endorsed by ISACA.

To choose CISA practice tests based on specific domains and subdomains, click that link.

CISA 3B-4 Post-implementation Review Practice Test 001
10 questions • Single best answer
Question 1
An IS auditor is conducting a post-implementation review of a newly deployed claims-processing system at a large insurance company. Executive management has requested assurance that the significant investment delivered the value promised when the project was originally approved. Several months have now passed since go-live. Which of the following should the auditor examine FIRST?
    Question 2
    A retail organization deployed a new point-of-sale system just three weeks ago and has asked an IS auditor to begin the post-implementation review immediately. Sales and transaction volumes are still fluctuating widely as store staff continue to adjust to the new checkout process. What is the auditor's BEST course of action?
      Question 3
      A government agency completed a post-implementation review of a new licensing system and reported the project a clear success because it was delivered on time and within the approved budget. An IS auditor has been asked to assess the quality and completeness of that review. Which conclusion is MOST appropriate?
        Question 4
        During a post-implementation review of a bank's new loan-origination system, an IS auditor learns that the review was performed entirely by the same project team that designed, built, and delivered the system. The team's report concluded that all project objectives had been fully met. Which of the following is the auditor's MOST significant concern?
          Question 5
          An IS auditor is evaluating the post-implementation review of an enterprise procurement system. The approved business case projected a 20 percent reduction in purchase-order processing costs within the first year of operation. Management now asserts that this target has been met. Which of the following provides the BEST evidence that the benefit was actually achieved?
            Question 6
            A healthcare provider's post-implementation review of a new electronic health record system found that the expected clinical-efficiency gains have not materialized six months after go-live. Clinicians report that the system works reliably, but many routine processes now feel slower than before. Which recommendation should the IS auditor consider MOST appropriate?
              Question 7
              During a post-implementation review of a logistics company's new transportation management system, an IS auditor wants to confirm that the automated application controls designed during the project are functioning as intended now that the system is live in production. Which of the following approaches would provide the BEST assurance?
                Question 8
                A post-implementation review of a manufacturer's new warehouse management system reveals that no process was ever established to measure whether the projected inventory-accuracy improvements are being achieved. Management is satisfied simply because the new system runs smoothly each day. Which of the following is the MOST significant implication of this finding?
                  Question 9
                  An IS auditor is planning a post-implementation review of a recently deployed customer billing system at a utility company. To evaluate objectively whether the project met its objectives, the auditor must first establish the criteria for success. Which of the following sources provides the MOST reliable basis for defining those criteria?
                    Question 10
                    An IS auditor has completed a post-implementation review of a public university's new student information system and documented several unrealized benefits along with valuable lessons learned about scope and cost estimation during the project. To maximize the organizational value of these results, which action should the auditor recommend?