CISA Domain 4A-6 Practice Test 002

This practice test covers Domain 4 (Information Systems Operations & Business Resilience) Subdomain A-6 (Systems Availability and Capacity Management) from the CISA exam content outline.

These questions are inspired by the ISACA CISA exam and are designed to help you test your knowledge of information systems auditing, governance, risk management, IT operations, business resilience, and information asset protection.

These are not official exam questions or brain dumps. They are original scenario-based questions created to reflect the audit judgment, control evaluation, and risk-based decision-making skills tested in the CISA exam.

Note: CISA and Certified Information Systems Auditor are registered trademarks of ISACA. This content is not affiliated with or endorsed by ISACA.

To choose CISA practice tests based on specific domains and subdomains, click that link.

CISA 4A-6 Systems Availability and Capacity Management Practice Test 002
10 questions • Single best answer
Question 1
An external IS auditor at an airline reservation service provider is evaluating whether reported availability supports the 99.95 percent uptime commitment in customer contracts. Management provides monthly dashboards generated by the same operations team that is responsible for meeting the target. Which audit procedure provides the BEST assurance over the reported availability figures?
    Question 2
    During a capacity management audit at a regional stock exchange, the IS auditor notes that the trading platform's utilization thresholds were set five years ago and have never been revisited. Transaction volumes have since doubled, and several near-capacity alerts were recently dismissed as false positives. What should the IS auditor do FIRST?
      Question 3
      A mid-sized insurer's IT steering committee approves infrastructure budgets annually, but capacity plans are prepared by individual system administrators without input from business units. An IS auditor learns that two product launches last year caused unplanned performance degradation in customer-facing systems. Which recommendation is MOST appropriate?
        Question 4
        An IS auditor reviewing a hospital's electronic health record platform finds that the primary and failover database servers are housed in the same rack and share a single power distribution unit. Management notes that failover testing was completed successfully last quarter and considers availability risk adequately addressed. Which conclusion is MOST appropriate?
          Question 5
          A software-as-a-service provider relies on public cloud auto-scaling to handle demand for its customer portal. During an audit, the IS auditor discovers that the cloud account's service quota caps the number of compute instances, and no one monitors how close peak usage comes to that ceiling. Which risk is MOST significant?
            Question 6
            An IS auditor at a national retail bank is testing whether capacity management procedures operated effectively throughout the audit period. The procedure requires monthly capacity reports to be reviewed by the infrastructure manager, with identified remediation actions tracked through to closure. Which testing approach is MOST appropriate?
              Question 7
              A follow-up audit at a logistics company examines management's remediation of a prior finding that no capacity plan existed for the warehouse management system. Management provides a newly approved capacity plan, but utilization data shows the system still reached 98 percent CPU during last month's peak shipping period. What is the auditor's BEST course of action?
                Question 8
                A government benefits agency reports 99.9 percent availability for its online claims portal each quarter, yet citizens frequently complain that the portal times out during month-end filing periods. An IS auditor determines that availability is measured by a server ping every fifteen minutes. Which finding is MOST significant?
                  Question 9
                  An audit manager is planning an availability and capacity management audit at a manufacturing firm that operates more than two hundred applications. Available audit resources allow detailed testing of only a limited number of systems during the engagement. Which approach is MOST appropriate for selecting the systems to include in scope?
                    Question 10
                    A payment card processor's IS auditor reviews controls over maintenance windows for its authorization platform. Scheduled maintenance is approved through change management, but windows are frequently extended beyond agreed limits without notifying the business, occasionally breaching service levels. Which control would BEST reduce this availability risk?