CISA Domain 3A-1 Practice Test 002

This practice test covers Domain 3 (Information Systems Acquisition, Development & Implementation) Subdomain A-1 (Project Governance and Management) from the CISA exam content outline.

These questions are inspired by the ISACA CISA exam and are designed to help you test your knowledge of information systems auditing, governance, risk management, IT operations, business resilience, and information asset protection.

These are not official exam questions or brain dumps. They are original scenario-based questions created to reflect the audit judgment, control evaluation, and risk-based decision-making skills tested in the CISA exam.

Note: CISA and Certified Information Systems Auditor are registered trademarks of ISACA. This content is not affiliated with or endorsed by ISACA.

To choose CISA practice tests based on specific domains and subdomains, click that link.

CISA 3A-1 Project Governance and Management Practice Test 002
10 questions • Single best answer
Question 1
A state transportation agency's internal audit manager reviews governance of a $60 million toll system replacement. Monthly reports to the steering committee have shown green status for six months, yet the project's earned value data shows a schedule performance index of 0.78 and a cost performance index of 0.85. Which finding is MOST significant?
    Question 2
    An IS auditor at a regional credit union reviews a core banking upgrade that uses a stage-gate methodology. The project entered the build phase after the executive sponsor gave verbal approval, although the design gate review had not been held and several design deliverables remained in draft. What is the MOST appropriate recommendation?
      Question 3
      During an audit of a cloud data platform project at a pharmaceutical distributor, the project manager states that project risks are actively managed. The risk register lists 42 risks, each with an owner, rating, and planned response. Which of the following provides the BEST evidence that risk management is operating effectively?
        Question 4
        A hospital system's electronic health record optimization project has absorbed 14 scope changes since approval. The IS auditor finds that the project manager approved each change directly, and none included an assessment of impact on cost, schedule, or expected benefits. Which risk is MOST significant from a project governance perspective?
          Question 5
          An insurance company closed its claims automation project after go-live, and the project team was reassigned. Six months later, an IS auditor finds that no one is measuring whether the projected 25% reduction in claims processing time has been achieved. Which recommendation is MOST appropriate?
            Question 6
            A municipal government engages a systems integrator on a time-and-materials basis to implement a permitting system. The IS auditor finds that the project manager approves all vendor invoices, and invoiced hours are not reconciled to approved timesheets or accepted deliverables. Which control would BEST address this weakness?
              Question 7
              At a national airline, a crew scheduling system project is six weeks behind schedule, and the regulatory go-live date cannot move. The project manager plans to cut user acceptance testing from four weeks to one week and has not informed the steering committee. What is the IS auditor's BEST course of action?
                Question 8
                A global logistics firm runs three concurrent projects that each modify the customer master data structure. Each project has its own steering committee, and the IS auditor finds conflicting design decisions and duplicated data migration effort. Which recommendation would MOST effectively address the root cause?
                  Question 9
                  A telecommunications provider's billing replacement project has spent $18 million of a $20 million budget, and revised estimates show another $15 million is needed. Some executives argue the project must continue because so much has already been invested. On what basis should the steering committee MOST appropriately decide whether to continue?
                    Question 10
                    A fintech startup delivers its mobile lending app using Scrum, and the board asks internal audit whether project governance is effective. Velocity charts are strong, but the product owner lacks authority to prioritize the backlog, and features are often reprioritized by the CEO between sprints. Which conclusion is MOST appropriate?