CISA Domain 3B-1 Practice Test 002

This practice test covers Domain 3 (Information Systems Acquisition, Development & Implementation) Subdomain B-1 (System Readiness and Implementation Testing) from the CISA exam content outline.

These questions are inspired by the ISACA CISA exam and are designed to help you test your knowledge of information systems auditing, governance, risk management, IT operations, business resilience, and information asset protection.

These are not official exam questions or brain dumps. They are original scenario-based questions created to reflect the audit judgment, control evaluation, and risk-based decision-making skills tested in the CISA exam.

Note: CISA and Certified Information Systems Auditor are registered trademarks of ISACA. This content is not affiliated with or endorsed by ISACA.

To choose CISA practice tests based on specific domains and subdomains, click that link.

CISA 3B-1 System Readiness and Implementation Testing Practice Test 002
10 questions • Single best answer
Question 1
An audit manager at a pharmaceutical manufacturer is reviewing the readiness of a new laboratory information management system scheduled for go-live in two weeks. User acceptance testing is complete, but every sign-off form was signed by the IT project manager rather than by laboratory process owners. What should the audit manager recommend FIRST?
    Question 2
    During a pre-implementation review of a credit union's new online banking platform, an IS auditor finds that the test environment was loaded with a full copy of production member data, including account numbers and national identification numbers. Developers and contract testers have broad access to this environment. Which finding is MOST significant?
      Question 3
      A state transportation agency's new toll collection system passed functional and user acceptance testing. Two days before go-live, a late change to the fare calculation module was moved into the test environment and verified only by the developer who wrote it. What is the IS auditor's BEST course of action?
        Question 4
        An IS auditor is evaluating go-live readiness for an airline's new crew scheduling system. The steering committee plans to make the implementation decision next week, but no documented go/no-go criteria exist, and the vendor has stated that the system is ready. Which recommendation is MOST appropriate?
          Question 5
          A hospital network is preparing to implement a new pharmacy dispensing system. The IS auditor reviews the test summary and notes 14 open defects, including two high-severity defects affecting dosage calculations. The project sponsor wants to proceed and resolve the defects after go-live. What should the IS auditor do FIRST?
            Question 6
            An online retailer plans to launch a redesigned checkout platform just before its peak holiday season. The IS auditor notes that functional, integration, and user acceptance testing were completed successfully, but all testing used transaction volumes typical of an average business day. Which additional testing is MOST important before go-live?
              Question 7
              An IS auditor at a logistics provider reviews test documentation for a new freight billing system before its production release. All test scripts were executed and passed, but there is no traceability matrix linking approved business requirements to specific test cases. Which risk is of GREATEST concern to the IS auditor?
                Question 8
                A municipal government is replacing its property tax system and will run the legacy and new systems in parallel for two billing cycles. The IS auditor has been asked to evaluate the results of the parallel run. Which evidence provides the BEST assurance that the new system is ready for production?
                  Question 9
                  A regional bank's IT department performed all system and user acceptance testing for a new wire transfer module, using test scripts written by the developers. Business users from the payments operations team did not participate in designing or executing the tests. Which conclusion is MOST appropriate based on this evidence?
                    Question 10
                    During an implementation readiness review for a university's new student information system, an IS auditor learns that security testing will be performed after go-live to meet the semester start date. Role-based access profiles for faculty, staff, and students have been configured but not yet tested. Which recommendation is MOST appropriate?